North Church Court:
102 N. Church Court- Calvary Youth Build-
This project is rapidly moving along under the guidance of Carl Van Son.

The rough plumbing and electrical is completed and the interior walls are finished. Flooring and Cabinets are projected to be finished by the end of March. Jeanne Nettles and her daughter look forward to an April move-in date.

The duet at 104/106 North Church Ct. is progressing. The homes recently underwent the rough inspection phase for plumbing, electrical and framing.

With the drywall phase going on now we are looking at full completion in April. Marilyn Hintze and Sallee Davis along with their children look forward to becoming neighbors in May.

Oak Hollow Circle-Thrivent Build
More than 50 people were in attendance at the dedication of 17021 Oak Hollow. This project was completed with the help of Thrivent, a financial services company along with Peace Lutheran, Grace Lutheran and Truckee Lutheran Presbyterian. Pastor Ed Hilton from the Truckee Lutheran-Presbyterian Church was on hand to preside over the official program.

A formal reception at Grace Lutheran Church was coordinated by parishioner Michael Biolchini. The many people who helped build this home were able to enjoy refreshments and memories.

Jan Rogers, a member of Truckee Lutheran-Presbyterian Church presented Donna Reynolds and all four of her children with hand- made quilts for their new bedrooms. A representative from Thrivent presented a door knocker for the entrance to the new home.

Ivy Street
The Ivy Street project in Grass Valley was approved by the city council on October 10th. We are now in the process of creating a budget and construction timeline for this exciting new development. Infrastructure work is slated to take place in spring of 2007. Construction of the single duet and three individual homes will begin in early summer.